Special inspections and third-party testing: what contractors need to manage

By Scavi Company · · 3 min read
Special inspections and third-party testing: what contractors need to manage

Special inspections are required for critical structural work on many commercial projects. Here is how contractors keep them from becoming delays.

What special inspections are

Special inspections are third-party inspections required by the building code for critical structural elements, separate from the routine inspections done by the building department. They are common on commercial projects and cover work like structural steel, concrete, masonry, soils and fireproofing.

Who hires the inspector

In most cases, the owner or the owner's design professional hires the special inspection agency, not the contractor, to keep the inspection independent. The requirements are listed in a statement of special inspections that is part of the permit documents.

Keep reading — free

The rest of this article is worth the 20 seconds

Tell us where to send it and the full piece unlocks right here, along with everything else on this blog.

Rather just talk? Message us on WhatsApp.

Read the statement early

Review the required inspections and tests during preconstruction. They affect your schedule, your sequencing and when work can be covered up. Missing an inspection before a pour can mean coring, testing or tearing out work later.

Common inspections and tests

  • Concrete cylinders, slump and placement observation.
  • Rebar placement before the pour.
  • Bolting and welding on structural steel.
  • Soil compaction and bearing verification.
  • Masonry grout and reinforcement.

Schedule inspections like trades

Put inspections in your look-ahead schedule with lead times. Confirm the day before and make sure the work is ready. Inspectors who arrive to unfinished work cost time and often a return-trip fee.

Track the reports

Keep a log of every inspection, its result and open items. Nonconformances must be resolved and documented before the final report. A clean log speeds up closeout and the certificate of occupancy.

Work with the inspector, not against them

Inspectors are there to verify the work meets the design. Clear communication, access and organized documentation make inspections faster and reduce disputes.

Bring subs into the loop

Make sure the trades whose work is inspected know the requirements and the inspection points. The sub who pours before the rebar inspection creates a problem for everyone.

Budget for retests and reinspections

Failed tests and return trips often cost money. Clarify in your contract and with the owner who pays for reinspections caused by work that was not ready or did not pass. Clear terms prevent arguments when the invoice shows up.

Close out cleanly

Collect the final special inspection report before closeout. The building official often needs it before issuing the certificate of occupancy, so a missing report can delay the owner's move-in.

Run tighter jobs and win the right ones.

We help construction companies build the systems, online presence and client relationships that bring better projects.

Frequently asked questions

Who hires the special inspector?

In most cases the owner or the owner's design professional hires the special inspection agency, to keep the inspections independent from the contractor whose work is being inspected.