Money

Construction loans and how owners fund the job: the questions to ask before you sign

By Scavi Company · · 13 min read
Construction loans and how owners fund the job: the questions to ask before you sign

Contractors study the plans, walk the site and negotiate the specifications, and then sign without asking the question that determines whether they get paid: where is the money coming from, and what has to happen before it reaches us. A job funded by a bank construction loan behaves nothing like one funded by cash or by a developer's equity partner. Understanding the structure in advance converts most payment surprises into scheduled events, and it explains owner behavior that otherwise looks arbitrary.

Why the contractor should care how the owner is funded

Contractors examine plans, specifications and site conditions carefully, then sign contracts without ever asking the most consequential question about the project: where is the money coming from, and what has to happen before it reaches us. A project funded from a bank construction loan behaves differently from one funded by cash, and both behave differently from one funded by a developer's equity partner or by a lender who will not release funds without an inspection.

Almost every payment problem that is not a dispute about the work is actually a funding problem. Understanding the structure in advance turns surprises into scheduled events.

The ways owners fund construction

  • Cash. The simplest and least common at scale. Payment depends only on the owner's willingness and process.
  • Construction loan. Funds released in draws against completed work, verified by an inspection and administered by the lender or a title company.
  • Construction-to-permanent loan. The same structure that converts to a mortgage at completion, adding pressure to hit a completion date tied to rate locks.
  • Owner equity plus debt. Common in development, where the owner's equity is typically spent first and the lender funds afterward.
  • Public funding. Appropriated budgets with fiscal-year timing, formal payment cycles and statutory prompt payment rules.
  • Institutional or grant funding, which can carry reporting obligations and release conditions unrelated to construction progress.

Keep reading — free

The rest of this article is worth the 20 seconds

Tell us where to send it and the full piece unlocks right here, along with everything else on this blog.

Rather just talk? Message us on WhatsApp.

How a draw actually works

On a typical construction loan, the sequence runs like this. The contractor submits a pay application for work completed through a cutoff date, supported by a schedule of values and lien waivers. The owner reviews and approves it. The lender orders an inspection to verify that the work claimed has in fact been performed. A title company may run an updated title search to confirm no liens have been filed. The lender then funds the draw, the owner pays the contractor, and the contractor pays subcontractors and suppliers.

Each step takes time, and the cumulative interval between the cutoff date and money in the contractor's account is routinely thirty to forty-five days, sometimes longer. That interval, not the payment terms written in the contract, is what the contractor is actually financing.

The questions to ask before signing

  • Is the project financed, and has the loan closed, or is it still in commitment?
  • Who administers the draws, and what is the published draw schedule?
  • What documentation does the lender require with each draw, and in what format?
  • Is there an inspection requirement, and who schedules it?
  • Is retainage held by the owner, by the lender, or both?
  • How much owner equity is required, and has it been contributed?
  • Is there an interest reserve, and what happens if the job runs past its term?

Asking these is normal commercial diligence, not distrust. Sophisticated owners answer readily; evasive answers are themselves information.

The draw package, and why it gets rejected

Most late payments on funded projects are not decisions. They are rejections, and rejections are almost always about the package rather than about the work.

A complete draw package typically includes the pay application with the schedule of values updated to show work completed this period and to date, a corresponding progress schedule update, conditional lien waivers from the contractor and from every subcontractor and supplier billing in the current period, unconditional waivers covering the previous period's payments, certified payroll where required, stored material documentation with invoices and photographs, and any inspection or testing reports the contract requires as a condition of payment.

The waiver chain is where packages fail most often. A single missing subcontractor waiver can hold an entire draw, which means the general contractor is financing the whole project because one supplier's office was slow. The remedy is procedural: require waivers from subcontractors before the general's own cutoff date, make the following month's payment contingent on receiving the previous month's waiver, and keep a tracking sheet rather than relying on memory.

A second common rejection is arithmetic. Percentages complete that do not match the inspector's observation, line items billed beyond their scheduled value, or retainage calculated inconsistently all trigger a return of the application. Reviewing the application against the inspector's likely view before submitting takes twenty minutes and saves a month.

The equity-first trap

Many construction loans require the owner to spend their own equity before the lender advances anything. This creates a specific and predictable risk pattern: early payments are smooth because the owner is writing checks, and then, at the moment the equity is exhausted, payment slows while the first lender draw works through inspection and title.

Contractors who do not know this structure interpret the slowdown as a sign the owner is in trouble, or worse, do not notice it until two pay applications are outstanding. Knowing that the transition point exists allows the contractor to plan cash around it and to ask, in advance, when the equity is expected to be fully deployed.

Interest reserve and why a delay costs the owner twice

Construction loans typically include an interest reserve, an amount set aside to pay interest during construction. It is sized on an assumed schedule. When the project runs long, the reserve depletes, and the owner must fund interest from other sources, which is precisely when they become least able to approve change orders.

This explains owner behavior that otherwise looks irrational. An owner who enthusiastically approved changes in month three and fights every request in month eleven is often not being difficult; they are watching an interest reserve run dry. Contractors who recognize the pattern raise change orders earlier and price time extensions with an understanding of what they cost the other side.

The schedule of values as a cash flow tool

The schedule of values determines when the contractor gets paid for work, and it is negotiated once, at the beginning, when nobody is thinking about cash. Two legitimate practices matter here.

First, ensure that early-phase work carries appropriate value, since mobilization, site work and foundations consume significant cash before anything visible exists. Second, break the schedule into enough line items to bill accurately for partial completion, because a small number of large lumps means work performed cannot be billed until a whole item is finished.

What is not legitimate is front-loading beyond the actual value of early work. Lenders and their inspectors look for exactly that, and a schedule of values that appears unbalanced invites scrutiny of every subsequent application.

Stored materials and paying for what is not installed

Materials purchased but not yet installed are a large cash exposure, particularly for trades with long-lead equipment. Most contracts permit billing for properly stored materials, subject to conditions: materials stored at an approved location, insured, documented with invoices and photographs, and sometimes accompanied by a bill of sale transferring title.

The conditions are worth meeting, because the alternative is financing major equipment for months. Confirm the specific requirements at the preconstruction meeting rather than discovering the lender's rules when the first invoice for a switchgear order is rejected.

Public funding behaves differently

Projects funded from public budgets follow rules that have little in common with bank lending, and contractors moving between the two markets are frequently caught out.

Timing is dictated by fiscal years and appropriations rather than by draws. Work that spans a fiscal year boundary may face a pause while a new budget is adopted, and funds appropriated for one purpose generally cannot be moved to another, which is why change orders on public work often require a formal amendment process that takes far longer than the equivalent decision on private work.

In exchange, public work usually offers protections that private work does not. Prompt payment statutes commonly set deadlines for payment to the prime contractor and for the prime's payment to subcontractors, sometimes with interest accruing on late amounts. Payment bonds are typically required on public projects, which gives subcontractors and suppliers a remedy where mechanics liens against public property are unavailable. Retainage rules are frequently set by statute rather than by negotiation.

The practical advice is to learn the specific statutory framework in the jurisdiction before bidding, because the deadlines for making a bond claim are strict and unforgiving. A contractor who assumes public work operates like private work tends to discover the difference at the exact moment a claim period has just expired.

Warning signs that funding is failing

  • Pay applications approved but payment arriving late and later.
  • Requests to reduce or defer billing to a future month.
  • Change orders acknowledged verbally but never executed.
  • The owner asking the contractor to order materials directly and be reimbursed later.
  • Inspection or title steps taking longer without explanation.
  • Other trades on site reporting the same slowdown.
  • The owner's lender or title company changing mid-project.

Any one of these can be innocent. Two or three together justify a change in behavior: tighter credit control, immediate lien notice compliance and a direct conversation.

Protecting the company when funding wobbles

The protections are unglamorous and effective. Preserve lien rights from the start by filing any required preliminary notices on every job, not merely on jobs that look risky. Bill promptly and completely, since a contractor whose applications are always late has less standing to complain about payment. Keep subcontractor payment obligations aligned with what is actually received, within the limits of the law and the subcontract.

Most importantly, set an exposure limit before starting and enforce it. When unpaid work exceeds that limit, the response is a documented conversation and, if necessary, a suspension of work in accordance with the contract's provisions. Contractors rarely fail because one owner ran out of money; they fail because they continued working for six months after learning it.

Suspending work without losing the contract

Many contracts contain a right to suspend performance for non-payment, typically after written notice and a cure period. Using that right correctly requires following the stated procedure precisely: written notice, the contractual waiting period, and a clear statement of the amount outstanding. Stopping work without following the process can constitute breach and expose the contractor to termination for default.

When the process is followed, suspension is often unnecessary, because the notice itself prompts payment. The notice works precisely because it is credible, and it is credible only when the contract permits it.

The cash math of a funded project

Consider a six-million-dollar project with a contractor gross margin of eleven percent and a typical draw cycle.

  • Monthly billing in peak months: about 750,000 dollars.
  • Interval from cutoff to payment: 38 days average.
  • Retainage at five percent withheld: 37,500 dollars per month accumulating.
  • Peak working capital required: roughly 1.2 million dollars, which is well above the total gross margin of 660,000 dollars on the entire job.

That last comparison is the one every contractor should internalize. The cash tied up in a project routinely exceeds the profit the project will ever produce, which is why a single funding failure can be fatal to a company that was, on paper, doing well.

Where to start

Add the funding questions to your standard preconstruction checklist and ask them before signing, not after. Confirm the draw calendar and the documentation format at the first meeting and calendar the cutoff dates. File preliminary notices on every project as routine. Set a written exposure limit per owner. And review, for your current jobs, what the actual interval from cutoff to cash has been, because most contractors discover it is a week or two longer than they believed, and that discovery alone changes how they plan the next year.

Know how the job is funded before the first invoice.

We help contractors read the funding structure, build a schedule of values that matches real cash needs and set exposure limits that keep one owner from taking the company down.

Frequently asked questions

How long does a construction loan draw take?

Longer than the payment terms in the contract suggest, because the draw involves several sequential steps. The contractor submits a pay application supported by the schedule of values and lien waivers, the owner reviews and approves it, the lender orders an inspection to verify the work claimed, a title company may run an updated search to confirm no liens have been recorded, and only then are funds released to the owner, who pays the contractor. The cumulative interval from the billing cutoff date to money in the contractor's account is routinely thirty to forty-five days and sometimes more. That interval, not the stated payment terms, is what the contractor is actually financing on every project.

Why does an owner approve change orders early and fight them later?

Frequently because of the interest reserve. Construction loans typically include an amount set aside to cover interest during the construction period, sized on an assumed schedule. When a project runs long, that reserve depletes and the owner has to fund interest from other sources, which arrives at precisely the moment they are least able to approve additional cost. The same owner who enthusiastically approved changes in month three may resist every request in month eleven without being unreasonable. Contractors who understand this pattern raise change orders as early as possible, price time extensions knowing what delay costs the other side, and avoid saving up a batch of changes for the end of the job.

What is the most common reason a draw gets rejected?

Incomplete lien waivers. A single missing waiver from one subcontractor or supplier can hold an entire draw, which means the general contractor effectively finances the whole project because one office was slow. The remedy is procedural rather than diplomatic: require waivers from subcontractors before the general's own billing cutoff, make each month's payment contingent on receiving the prior period's waiver, and track them on a sheet rather than from memory. The second most common cause is arithmetic that does not match the inspector's view, such as percentages complete that overstate progress or line items billed beyond their scheduled value, both of which trigger a return of the application.